KUKL PID WORK PROGRESS

WORK PROGRESS SUMMARY
BDS: 49.94 km out of 60.6 km
DNI: 612.80 km out of 670 km

 Package: DNI 2 Primary

Mahankal Chaur RVT to Baudhik Marg
Today: 0 m To Date: 635 m Total: 3085 m
Pipe Diameter: 1000 mm

Baudhik Marg to Mitra park
Today: 0 m To Date: 865 m Total: 1602 m
Pipe Diameter: 900 mm

Mitra park to Gaushalla
Today: 0 m To Date: 335.5 m Total: 613 m
Pipe Diameter: 800 mm

Gaushalla to Ratopool
Today: 0 m To Date: 0 m Total: 620 m
Pipe Diameter: 600 mm

Ratopool to Dhobikhola crossing
Today: 0 m To Date: 0 m Total: 35 m
Pipe Diameter: 500 mm